The following data relate to two output levels of a department:
Machine hours 17,000 18,500
Overheads $246,500 $251,750
What is the amount of fixed overheads?
$ O
The following data relate to two output levels of a department:
Machine hours 17,000 18,500
Overheads $246,500 $251,750
What is the amount of fixed overheads?
$ O
$
Total cost of 18,500 hours 251,750
Total cost of 17,000 hours 246,500
Variable cost of 1,500 hours 5,250
Variable cost per machine hour = $5,250/1,500 machine hours = $3.50.
$
Total cost of 17,000 hours 246,500
Less variable cost of 17,000 hours (x $3.50) 59,500
Balance = fixed costs 187,000