题目

 Calculate the overhead cost of centre hire which would be allocated to an auditing course under activity based costing to the nearest dollar. 

扫码查看暗号,即可获得解锁答案!

点击获取答案
考点:Chapter2aActivitybasedcosting

Overhead cost of centre hire per auditing course using activity based costing 

Number of days per auditing course = 2 

Centre hire cost per auditing course = 2 × $328.95 = $657.90 

多做几道

 Actual overheads cost $180,000 and 40,000 machine hours were worked. 

Actual overheads cost $170,000 and 40,000 machine hours were worked. 

材料全屏
5

【论述题】

Prepare profit statements for each period and for the two periods in total using both absorption costing and marginal costing. 

材料全屏
6

【论述题】

Prepare profit statements for each of the six-monthly periods, using the following methods of costing. 

Marginal costing 

Prepare profit statements for each of the six-monthly periods, using the following methods of costing. 

Absorption costing 